49 Sub Station , Pump Stn # 6 Design , Supply, Installation of FM-200 Fire Protection System at Pump Stn # 6. Saudi Aramco / Nesma
50 Wet Chemical Kitchen Fire Protection System Supply, Engineering, Installation, Testing Commissioning of Wet Chemical Fire Protection System in Saudi Aramco Dahran- 5 areas Saudi Aramco
51 Wet Chemical Kitchen Fire Protection System Supply, Engineering, Installation, Testing Commissioning of Wet Chemical Fire Protection System in Saudi Aramco Abqaiq – 2 areas Saudi Aramco
52 Server Room Design , Supply, Installation of FM-200 Fire Protection System at Server Room EniRepSa Gas Ltd / MTTS
53 Server Room Design , Supply, Installation of FM-200 Fire Protection System at Server Room Zamil operations & Maintenance
54 Hazardous Chemical Warehouse Design , Supply, Installation of Water Sprinkler System , Hose Cabinets , & Hydrant System for Chemical Warehouse. SWCC – Al Khobar
55 Eastern Water Tower – Al Khobar Supply, Engineering, Installation, Testing Commissioning of Water Sprinkler System , FM- 200 System, CO2 System in Water Tower ( on going ) Saudi Technical
56 Al Hugayat Tower – Al Khobar Supply, Engineering, Installation, Testing Commissioning of Water Sprinkler System Tower ( on going ) ATCO
57 Saudi Aramco – Khafji Supply, Engineering, FM-200 Fire Protection System Angus Fire UK
58 KFUPM – Bldg # 14 Supply, Engineering, Installation, Testing Commissioning of FM- 200 System for Bldg # 14. ( on going ) KFUPM
59 Warehouse – Tabuk Deluge Foam Spray System in warehose complete with design, supply and installation. Tabuk Pharm. Company
60 60 Shifting of 5000 GPM fire fighting pump set. Complete shifting of fire fighting pump set at SWCC Al khobar. SWCC – Al Khobar